This alternative would include full replacement of the interchange
bridges while maintaining the present alignment of the roadways.
Construction of a new Route 10 northbound to Route 6 westbound movement
is not included. New foundations would be constructed between the
existing ones where possible, so that removal of the existing footings
and piles would not be required.